Projects
4M Partners Vietnam Projects
Projects of 4M Partners Vietnam

Construction of KCI Vina factory Phase 2 – Binh Xuyen, Vinh Phuc, Vietnam
2017 - 2018

Construction of KCI Vina factory Phase 2 – Binh Xuyen, Vinh Phuc, Vietnam
Client
KCI Vina Co., Ltd.
PROJECT SCOPE
Project location: Lot CN06-8, Binh Xuyen II IZ, Ba Hien Commune, Binh Xuyen District, Vinh Phuc Province, Vietnam
1. Purpose of Building: Computer component manufacture
2. Land Area: 27268,48 m2
3. No. of storeys: 2 Floors
4. Total building areas: 24386 m2
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
November 2017 ~ April 2018

Factory II of Jeil Jersey Vina – Vu Hoi, Vu Thu, Thai Binh, Vietnam
2020

Factory II of Jeil Jersey Vina – Vu Hoi, Vu Thu, Thai Binh, Vietnam
Client
Jeil Jersey Vina Co., Ltd.
PROJECT SCOPE
Project location: Vu Hoi Industrial Cluster, Vu Hoi Commune, Vu Thu District, Thai Binh Province
1. Purpose of Building: Factory
2. Land area: 3.25 ha
3. No. of storeys: 02 storeys
4. Total building areas: 18,959.5 m2
4M PARTNERS PROVIDES:
Construction Management & Supervising
CONTRACT PERIOD
March 01, 2020 ~ July 31, 2020

CT11 & CT12 Building of Tu Hiep – Thanh Tri, Hanoi, Vietnam
2017 - 2020

CT11 & CT12 Building of Tu Hiep – Thanh Tri, Hanoi, Vietnam
Client
Tu Hiep Hong Ha Petrolium JSC.
PROJECT SCOPE
Project location: Thanh Tri, Hanoi, Vietnam
1. Purpose of Building: Apartments
2. Land Area: 8,614 m2
3. Number of storeys: 27 floors (CT11) & 22 floors (CT12)
4. Total Building Areas: 57,809 m2 & 9,120 m2 Basement
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
March 2017 ~ 2020

Shore Protection Embankment of Mipec Port – Hai An, Hai Phong, Vietnam
2017 - 2019

Shore Protection Embankment of Mipec Port – Hai An, Hai Phong, Vietnam
Client
Mipec Port JSC.
PROJECT SCOPE
Project location: Dinh Vu – Cat Hai Economic Zone, Hai Phong, Vietnam
1. Purpose of Building: Shore Protection Embankment
2. Land Area: 25,000 m2
3. Total length of embankment: 448,4 m
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
February 2017 ~ July 2019

Hyundai Hillsmall Commercial Center – Ha Dong, Hanoi, Vietnam
2016 - 2019

Hyundai Hillsmall Commercial Center – Ha Dong, Hanoi, Vietnam
Client
Hyundai RNC Ha Tay Co., Ltd.
PROJECT SCOPE
Project location: Ha Dong, Hanoi, Vietnam
1. Purpose of Building: Commercial Center
2. Land Area: 25,000 m2
3. No. of storeys: 02 basements + 01 floor of commercial area
4. Total building areas: 2,300 m2
4M PARTNERS PROVIDES:
Construction Management & Supervising
CONTRACT PERIOD
December 2016 ~ May 2019

Warehouse of Dorco Hung Yen Blade Factory – Van Lam, Hung Yen, Vietnam
2016 - 2017

Warehouse of Dorco Hung Yen Blade Factory – Van Lam, Hung Yen, Vietnam
Client
Dorco Vina Co., Ltd.
PROJECT SCOPE
Project location: Van Lam, Hung Yen
1. Purpose of Building: Warehouse
2. Site Area: 6,000 m2
3. Number of storeys: 01 floor
4. Total building areas: 6,000 m2
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
August 2016 ~ January 2017

LG Coil Center – Trang Due, Hai Phong, Vietnam
2015 - 2016

LG Coil Center – Trang Due, Hai Phong, Vietnam
Client
Hai Phong Steel Flower Electrical & Machinery Co., Ltd.
PROJECT SCOPE
Project location: Trang Due IP, Hai Phong
1. Purpose of Building: Steel Manufacturer
2. Site Area: 1,5 Ha
3. No. of storeys: 1 floor
4. Total building areas: 7,754 m2
4M PARTNERS PROVIDES:
Construction Management & Supervising
CONTRACT PERIOD
September 2015 ~ June 2016

STARLAKE VILLAS K3-TT1 & TT2, Tay Ho Tay New Town, Hanoi
2019 - 2021

STARLAKE VILLAS K3-TT1 & TT2, Tay Ho Tay New Town, Hanoi
Client
THT Development Co., Ltd.
PROJECT SCOPE
Project location: Tay Ho Tay, Hanoi, Vietnam
1. Purpose of Building: Villas
2. Site Area: 6 ha
3. Number of storeys: 3 floors
4. Total building areas: 65,000 m2
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
August 2019 ~ July 2021

GLONICS FACTORY PROJECT - THAI NGUYEN
2013 - 2016

GLONICS FACTORY PROJECT - THAI NGUYEN
Client
Glonics Co., Ltd.
PROJECT SCOPE
Project location: Phu Xa, Thai Nguyen City, Thai Nguyen Province
1. Purpose of Building: Headset manufacturing (Samsung Electronics First Vender)
2. Site Area: 66,780 m2
3. No. of storeys: 1 ~ 3 floors
4. Total building areas: 56,675 m2
4M PARTNERS PROVIDES:
Construction Supervising
CONTRACT PERIOD
July 2013 ~ January 2016